2021/22 Pool Project

Description of Project:

Establish a formal Engineered specification for the removal and replacement of the exterior pool concrete deck, wood deck, fence, and retaining walls in 3rd Quarter 2021. Obtain bids for the work with goal to complete the project in time to open the pool in 2022. Repair both septic systems.

Basis for Project:

The exterior concrete deck surrounding the pool is fractured and determined unsafe by the CCA Insurance provider expert; to remain insured we are fixing the pool. The existing retaining wall supporting the concrete, wood deck and fence was incorrectly built, is failing and the fence around the pool is rotted. The septic systems are non-functional. For Engineering Evaluation of Pool CLICK HERE.

Value to Membership:

Safety for all users of the pool.  Slipping and falling hazards reduced, concern over pool failure reduced (from deck failure), wood deck and fence failure concern eliminated. Improved protection of ground water and surrounding environment.

Preliminary Cost/ Schedule:

Contract awarded to MC2 Engineering June 2021 for ($2,000) to write the concrete and fence specification. A list of contractors has been assembled; we are preparing to solicit bids. Septic system work in progress. Specification due by 1st week in August. Total pool refurbishment project estimated at $250,000.  

For Structural Plan of the Pool Project Click Here
For Structural Calculations of the Pool Project Click Here
For the Request for Proposals for the Pool Project Click Here